From Product Data to a Verified EPD: A Roadmap for Data Center Suppliers
Author:
Luke Boivin

Turn your customer’s EPD request into a clear plan, from product data through independent verification and publication.
For manufacturers supplying data-center cooling equipment, piping, electrical systems and construction materials, the challenge is coordinating the work behind the declaration. Someone must define what the EPD covers, someone must build and document the life cycle assessment (LCA), and an independent reviewer must be able to follow the evidence.
This roadmap explains what each stage produces and how that work moves to the next person. The International EPD System’s development guidance provides one program’s view of the path. Confirm the requirements and verification route for your chosen program before commissioning the work.
Step 1: Confirm the Product Category Rules and Program
Start by agreeing which Product Category Rules (PCR) apply and which program operator will publish the declaration. The PCR sets the method for assessing and reporting the product, including the reference unit, life-cycle stages and data requirements.
These decisions shape the work that follows. A model built around one scope may need revision if the intended program requires a different boundary or reporting approach. If no suitable PCR exists, discuss the path with the program operator before proceeding.
The outcome of this stage is an agreed rule set and publication destination. The manufacturer and practitioner can then plan toward the same deliverable.
Step 2: Define What the Declaration Will Cover
Translate the commercial product into a precise assessment scope. Identify the configurations, manufacturing facilities and reporting period the declaration is intended to represent, together with the life-cycle stages required by the rules.
Consider an illustrative cooling-equipment family. Different capacities may share manufacturing steps while using different component quantities. The team needs to decide how those configurations will be modeled and represented before collecting data for just one unit and assuming it covers the rest.
The agreed scope becomes the reference for later decisions. A supplier record or facility total is useful only when the team can explain how it relates to the products being assessed.
Step 3: Collect Evidence the Practitioner Can Use
The manufacturer coordinates records from engineering, operations, procurement and logistics. The practitioner turns those records into usable model inputs and identifies the gaps that need a decision.
This is where the data-collection checklist earns its place. Bills of materials, facility energy, production output and transport records need units, dates and source evidence. Before finalizing the model, the team checks whether the records describe the same products and reporting period.
Some gaps may require an estimate or a secondary dataset. Preserve the reason for that choice alongside the input. The handoff should give the practitioner enough context to use the evidence and the reviewer enough context to understand it.
Step 4: Build a Model That Preserves the Evidence
The LCA practitioner connects the product and manufacturing inputs to background datasets and impact-assessment methods. The model calculates the required environmental indicators while preserving decisions about allocation, transport, waste treatment and other assumptions.
For a product family, common manufacturing logic can sit in a shared model structure. Configuration-specific inputs account for differences in material quantities, facilities or suppliers. The relationship between each result and its inputs must remain visible.
Quality checks test whether that structure behaves as intended. Units and balances should reconcile, dataset choices should fit the scope, and another reviewer should be able to follow how a result was produced. Those calculations become the basis for the technical documentation.
Step 5: Prepare the Technical Report and Public Declaration
The work now produces two related documents.
The LCA report explains the study’s scope, evidence, methods, assumptions and results in enough detail for review. It supports the technical assessment and may contain confidential product or manufacturing information.
The draft EPD presents the proposed public disclosure in the format required by the program. It includes the product information and environmental results buyers will receive.
The LCA report is the technical justification. The EPD is the public declaration built from that work.
Keep both documents connected to the same calculation revision. This gives the reviewer a consistent package and helps the manufacturer control which information belongs in the public declaration.
Step 6: Complete the Required Verification
For the independent-review route described here, the verifier evaluates the declaration and its supporting technical work against the applicable requirements. The person who prepares the LCA does not verify their own work.
The reviewer examines whether the scope, evidence and modeling choices support the reported results. A question about a material input may require a source record; a question about an allocation choice may require an explanation in the report.
Verification routes vary by program. The International EPD System also describes process certification and pre-verified tool routes, so confirm the applicable review requirements rather than assuming every declaration follows an identical process.
UL Solutions recommends organizing supporting records and communicating clearly with the verifier. Accessible evidence helps the practitioner answer questions without reconstructing earlier work.
Step 7: Resolve Questions Across the Whole Package
A verification comment may affect the model, report and declaration together. The response needs to follow the change through all affected outputs.
For example, correcting a material quantity may require a revised calculation, an updated result in the report and a matching change in the draft EPD. Copying a new number into only the declaration leaves the technical record inconsistent.
Keep the reviewer’s question, the response and the revised evidence together. Return the exact revision for confirmation so everyone knows which package has completed review.
Step 8: Register and Publish the EPD
Once verification and the required approvals are complete, the declaration moves through the program operator’s registration and publication process. Check the submission requirements for the chosen program rather than treating verification as the final administrative step.
The published declaration gives the commercial team a public reference it can share with buyers. Retain its registration details, validity information and URL alongside the approved technical revision.
Manufacturers can also make the EPD available through product pages and relevant databases. Check each receiving database’s submission route and product coverage so the declaration can be found where customers look for evidence.
Step 9: Keep the Evidence Usable After Publication
Publication establishes a baseline the manufacturer will need to maintain. A new supplier, material option or manufacturing process can affect the assumptions behind the declaration.
Retain the model, source records and verification history so the team can assess a change against the approved work. The applicable program rules determine whether an update or further review is needed.
A useful closeout record keeps three things easy to find:
The products, facilities and period covered by the declaration.
The approved calculation, supporting report and source evidence.
The published declaration and the conditions that trigger review.
This makes the next product change a reviewable update, rather than a search through disconnected files.
Build One Evidence Foundation for the Whole EPD Workflow
The manufacturer supplies product and operational evidence. The practitioner builds the model and technical documentation. The verifier independently reviews the work, and the program operator manages publication.
CarbonGraph helps manufacturers keep that work connected through reusable LCA models, source evidence and review-ready documentation. The same foundation can support product-configuration results, technical reports and EPD preparation, while each declaration follows its applicable rules and review requirements.
Start with the buyer’s requirement, agree the scope and keep the evidence connected through every handoff. That is how product data becomes a declaration the customer can use.
Want to see how the process would work for your product family? Book a walkthrough.